9 men taking 5 hours = 9 x 5 = 45 hour job

3 men doing a 45 hour job = 45 / 3 = 15 hours

User Avatar

Wiki User

6y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: If it takes 9 men 5 hours to do a job how long will it take 3?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

Two people are painting a fence one takes 3 hours to complete the job and one takes 6 hours to complete the same job how long would it take for both to complete the same job -?

It would still take six hours.


How many hours roughly do roofers work?

as long as the job takes


If 2 people take 6 hours to do a job how long will it take 1 people to do the same job how do you work this out?

Assuming the same rate of speed, if it takes 2 people 6 hours to do a job, it will take 1 person 12 hours to do the same job. In each case, the number of work hours (2 x 6, 1 x 12) is the same.


Two people are shoveling a driveway one takes 3 hours to complete the job and the other takes 2 hours how long will it take them working together?

it will take them 2 hours and a half to work together on the driveways. but it depends on how far the driveways are from each other


Two people are painting a fence one takes 3 hours to complete the job and one takes 6 hours to complete the same job how long would it take for both to complete the same job?

My somewhat educated guess would be two hours. The person who could complete the job in 3 hours could complete 2/3 of the job in two hours. The person that complete the job in 6 hours could complete 1/3 of the job in two hours. 2/3 + 1/3 = 1.


Worker A can complete a job in 20 hours and worker B can complete a job in 25 hours if both workers work together how long will it take them to complete the job?

The way to calculate this is to figure out what fraction each does in an hour (1/20 of the job, vs. 1/25 of the job). Add the fractions together to see how much they do together in an hour, then take the reciprocal to find out how many hours it takes them.


How long does it take to pull a tansmission from a 94 ford escort lx3?

The job takes 3.5 to 4.0 hours to pull the transmission estimate to rebuild it - $1,700


If it takes 9 workers 5 hours to do a job how long will it take 3 men?

fifteen 9 x 5 = 45 45 / 3 = 15


If a crew of 4 workers complete the job in 10 hours how long will it take 5 workers to complete the same job?

Eight hours.


A company has a machine that can complete a job in 6 hours A new machine can complete the job in 2 hours How long would it take the new machine to complete the job alone?

3 hours


If 2 men take 4 hours to do a job how long will 5 men take?

10 hrs


How long does it take gloss paint to dry?

between 24-48 hours depending on 1, the quality of the gloss, and 2, how thick you apply it. Have fun! Its a crap job!!!