Critical Path Method (CPM) is a step-by-step technique for process planning that defines critical and non-critical tasks with the goal of preventing time-frame problems and process bottlenecks. The CPM is ideally suited to projects consisting of numerous activities that interact in a complex manner. In applying the CPM, there are several steps that can be summarized as follows: * Define the required tasks and put them down in an ordered (sequenced) list. * Create a flowchart or other diagram showing each task in relation to the others. * Identify the critical and non-critical relationships (paths) among tasks. * Determine the expected completion or execution time for each task. * Locate or devise alternatives (backups) for the most critical paths. The CPM was developed in the 1950s by DuPont, and was first used in missile-defense construction projects. Since that time, the CPM has been adapted to other fields including hardware and software product research and development. Various computer programs are available to help project managers use the CPM.

User Avatar

Wiki User

16y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What is Critical Path Method?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

Where can someone find more information about the critical path method?

You can find more information about the critical path method in project management textbooks, online resources such as websites or blogs dedicated to project management, or by taking courses or attending workshops on project scheduling and management. Additionally, professional organizations like the Project Management Institute (PMI) may offer resources and guidance on the critical path method.


What is the M in CPM?

CPM : Critical Path Method


In netball what does cpm mean?

Critical path method


What are the Advantages and disadvantages of critical path method?

Critical Path Method (CPM) focuses on the time to complete the project and the other important activities on which a manager shall focus attention.


Full form of pert and cpm?

CPM -Critical Path Method


WHAT IS CRITICAL PATH METHOD IN SCHEDULING?

Critical Path Method (CPM) is the commonly used method by Project Managers for its simplicity and effectiveness. It is used for tracking/monitoring and control of a project. The critical path in construction schedule derives the project duration and there can be multiple critical paths in schedule depending upon the constraints and activities relationships, hence the entire project timeline could be lengthened by delaying activities along with any one of the critical paths.


What is CPM in project management?

CPM stands for Critical Path Method and it is a method to create Schedules for Projects


What has the author M Krishnamoorthy written?

M. Krishnamoorthy has written: 'Critical path method' -- subject(s): PERT (Network analysis), Critical path analysis


What is cpm and pert?

Critical Path Method (CPM) - A schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram.


What is critical chain method?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start dateThe important feature of the critical path method is to identify the flexibility in the project schedule by calculating the early and late start and finish dates of each activity on each path. The schedule flexibility of an activity is measured by the positive difference between the late start date and the early start date for the activity and is called float time or total float.


What is the different between critical path method and program evaluation and review technique?

Program Evaluation and Review Technique (PERT) lays the foundation of the network diagram or process by which the program will be completed. The Critical Path Method (CPM) is used within PERT to determine a critical path for a project within a program or the program itself if all the duration information is known for the program. CPM is a subset of PERT.


What is the significance of Critical Path Analysis in Project development?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date.The second important feature of the critical path method is to identify the flexibility in the project schedule by calculating the early and late start and finish dates of each activity on each path. The schedule flexibility of an activity is measured by the positive difference between the late start date and the early start date for the activity and is called float time or total float.Without a proper Critical Path Analysis, an efficient Schedule for the Project cannot be created