Any difference between the scheduled completion of an activity and the actual completion is know as schedule variation.

The objective of this metric is to measure the % of deviation and take corrective action to reduce it.

Formula = ((Actual End Date - Planned End Date)/(Planned End Date- Planned Start Date))*100

Metric

Phase

LCL

Goal

UCL

Schedule Variation

Overall

0.00

0.00

0.00

KT Stage

-1.90

0.20

2.29

Test Requirements Study Stage

-3.28

1.49

6.26

Test Design Stage

-2.80

0.00

2.80

Test Execution Stage

-2.43

0.10

2.63

LCL: Lower Control Limit

UCL: Upper control Limit

User Avatar

Wiki User

15y ago

Still curious? Ask our experts.

Chat with our AI personalities

RafaRafa
There's no fun in playing it safe. Why not try something a little unhinged?
Chat with Rafa
ProfessorProfessor
I will give you the most educated answer.
Chat with Professor
SteveSteve
Knowledge is a journey, you know? We'll get there.
Chat with Steve

Add your answer:

Earn +20 pts
Q: What is schedule variation in metrics?
Write your answer...
Submit
Still have questions?
magnify glass
imp