The electrical code states that there shall be no more than four 90 degree bends in a conduit length between pull boxes. This equals 360 degrees. The first scenario 90 + 90 + 45 + 45 + 45 + 45 = 360 degrees so that conduit run is acceptable. The second scenario 90 + 90 + 30 + 30 + 30 + 30 +30 = 330 degrees so this combination is also acceptable.