Best Answer

Shahid works 5 hours x 21 days which equals 105 hours. Divided by 3 sarees is 35 hours per saree. If you take 35 hours times 6 sarees it's 210 hours divided by 7 hours hours a day and the answer is 30 days.

User Avatar

Wiki User

10y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: Working five hours daily shahid can embroider three sarees in twenty one dayshow many days will it take for him to embroider six sarees working seven hours dailyanswer with solution?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

7 months of the year have 31 dayshow many have 28?

1 february


If 4 men can make 200 toys in 5 dayshow many toys will 10 men make in 7days?

1000


What TV show titles start with the letter H?

Howdie DoodieHomicide, Life on the StreetHogan's HeroesHawaii Five OHappy DaysHow Do I Look?


What are some recommended modern Christian worship songs?

Some timeless but modern Christian worship songs are:Here I am to WorshipAncient of DaysHow Great is our GodAmazing GraceBlessed be Your NameThe Heart of Worship


A main stitches 25 dresses in 5 dayshow many dresses does he make in 2 days?

25 dress in 5 days = 5 dresses a day, in 2 days that would be 10


10 men can complete a job in 14 dayshow long will it take 4 men to finish the same job if they work at the same rate?

Ans- It will take 4 men to complete the work in 35 days.


In a grass field if 40 cow could eat for 40 daysThe same grass field can feed 30 cows for 60 dayshow long will it feed 20 cows?

It will feed 20 cows in 80 days.


John does a job in 10 daysjack does a job in 5 dayshow long would it take both boys working together to complete the job?

John does (1/10) = 0.1 of the job each day. Jack does (1/5) = 0.2 of the job each day.Working together, they do (0.1 + 0.2) = 0.3 of the job each day.(1 job) / (0.3 job per day) = (3 and 1/3) days


13If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the same piece of work in 6 dayshow long will 6 men and 24 boys take to complete the same work?

In 4 days!


A farmer knows that 20 of his hens housed in 3 coops will hatch 30 eggs in 18 dayshow long will 30 hens housed in 4 coops to hatch the same number of eggs?

18 days - it always takes the same number of days (roughly) to hatch eggs.


If two women can dig two holes in two dayshow long does it take for one woman to dig half a hole?

Half a hole cannot be dug as it will always be a hole. However, to dig a hole half the size of the ones dug, It takes one woman one day to dig half a hole.


10 men and 15 women can finish awork in 6 days1 man can finish in 100 dayshow many days will a women take to finish her work?

-- 1 man can do the job in 100 days.-- Each day, 1 man does 0.01 of the job.-- Each day, 10 men do 0.1 of the job.-- In 6 days, 10 men do 0.6 of the job.-- If 15 women work with the 10 men, they can all finish the job in the same 6 days.-- So the 15 women must do the remaining (1 - 0.6) = 0.4 of the job in 6 days.-- Each day, the 15 women do 0.4/6 of the job.-- Each day, each woman does 0.4/(6 x 15) of the job.-- So it would take 1 woman (6 x 15)/0.4 days to do the job.That's 225days.(Does this mean that women should earn 100/225 = 44.4% the hourly wage of men ? ?)