No, there has to be a three foot clearance in front of the panel. This is so that electricians can work safely on the panel.
Chat with our AI personalities
How do i install aluminum bonding strap in sub panel of 100 amp service
No, you should not install anything in front or below the panel. You must have 36" of free space in front of the panel and 30" on either side of the panel.
yes wires is electrical panel
The top of the service panel can be no more than 6' 6" off the floor. Must be 36" of clearance in front of the panel and 30" on each side. Use common sense when installing the panel. If you install the top of the panel aroud 6' 2" off the floor you are good to go.
That depends on what you mean by "box in". You must always provide access to an electrical panel.