1 60lbs bag makes around a 1' by 1' by 3" thick pad..
To determine how many bags of concrete are needed for a slab measuring feet x feet x 4 inches, first convert the dimensions to cubic feet. A 4-inch thickness is equivalent to 0.33 feet, so the volume is calculated as length x width x 0.33. Then, divide the total cubic feet by the volume of a standard bag of concrete (usually 0.5 cubic feet). This will give you the number of bags required.
To make one cubic yard of concrete using Quikrete, you would need approximately 54 bags of 50-pound Quikrete. This is based on the fact that one cubic yard is equivalent to 27 cubic feet, and a 50-pound bag yields about 0.375 cubic feet of concrete. Therefore, dividing 27 cubic feet by 0.5 cubic feet per bag gives you about 54 bags.
One cubic yard is equivalent to 27 cubic feet. A 60-pound bag of Quikrete typically yields about 0.45 cubic feet of concrete. Therefore, to fill one cubic yard, you would need approximately 60 bags of 60-pound Quikrete bags (27 cubic feet ÷ 0.45 cubic feet per bag = 60 bags).
9.72 Cubic Yards of Concrete is required, if you are going to order by cement truck. 874.8 bags of 40# (40 lbs) bags, or 583.2 bags of 60# 437.4 bags of 80#
To calculate the number of 80 lb bags needed for a 3x4x3 pad, first determine the volume of the pad in cubic feet: 3 ft x 4 ft x 3 ft = 36 cubic feet. An 80 lb bag of concrete typically covers about 0.6 cubic feet. Therefore, you would need approximately 36 / 0.6 = 60 bags of 80 lb concrete to fill the pad.
To determine how many bags of concrete are needed for a 10x10 patio, you first need to calculate the volume of concrete required. A 10x10 patio is 100 square feet, and if you plan for a thickness of 4 inches (0.33 feet), the volume would be 100 sq ft x 0.33 ft = 33 cubic feet. Since standard concrete bags are typically 80 pounds and cover about 0.6 cubic feet, you would need approximately 55 bags of concrete (33 cubic feet ÷ 0.6 cubic feet per bag).
1.8 Cubic yards of concrete is 48.6 cubic feet. Each 80lb bag of concrete is .6 cubic feet. Therefore, you would need 81 bags. Hope that helps. GEO
To determine how many bags of concrete are needed for 1.78 cubic yards, first note that a standard bag of concrete typically contains 0.5 cubic feet. Since there are 27 cubic feet in a cubic yard, 1.78 cubic yards is equivalent to 1.78 x 27 = 48.06 cubic feet. Dividing 48.06 cubic feet by 0.5 cubic feet per bag gives approximately 96.12 bags. Therefore, you would need about 97 bags of concrete to cover 1.78 cubic yards.
There are approximately 27 cubic feet in a cubic yard, and an 80-pound bag of concrete typically yields about 0.6 cubic feet. Therefore, to fill one cubic yard, you would need about 45 bags of 80-pound concrete.
To calculate the number of concrete bags needed for a 10x10x2 foot slab, first find the volume in cubic feet: 10 x 10 x 2 = 200 cubic feet. A standard 80-pound bag of concrete typically covers about 0.6 cubic feet. Therefore, you would need approximately 334 bags (200 ÷ 0.6 ≈ 333.33) of concrete to fill that volume.
To determine how many bags of quick mix concrete are needed to cover 144 square feet, you first need to know the thickness of the concrete layer you plan to pour. For example, if you are pouring a thickness of 4 inches (0.33 feet), you would need approximately 1.33 cubic yards of concrete. Since one bag of quick mix concrete typically covers about 0.6 cubic feet, you would require around 40 bags (1.33 cubic yards equals about 36 cubic feet, and 36 divided by 0.6 equals 60 bags) to cover that area at that thickness. Adjust the number of bags based on the desired thickness.
The number of bags needed for 1500 psi concrete depends on the size of the bags and the volume of concrete required. Typically, a standard bag of concrete mix weighs 60 pounds and yields about 0.45 cubic feet. To determine the number of bags, calculate the total volume of concrete needed in cubic feet and divide it by the yield per bag. For example, for 1 cubic yard (27 cubic feet), you would need approximately 60 bags of 60-pound mix.
To determine how many bags of 80 lb concrete make a cubic yard, you need to know that one cubic yard is equivalent to 27 cubic feet. An 80 lb bag of concrete typically covers about 0.6 cubic feet. Therefore, to fill one cubic yard, you would need approximately 45 bags of 80 lb concrete (27 cubic feet ÷ 0.6 cubic feet per bag ≈ 45).
To calculate the number of bags of concrete needed for a 2x2x4 slab, first determine the volume of the slab in cubic feet: 2 ft x 2 ft x 4 ft = 16 cubic feet. Since a standard bag of concrete (typically 80 lbs) covers about 2 cubic feet, you would need approximately 8 bags (16 cubic feet ÷ 2 cubic feet per bag). Therefore, you would need 8 bags of concrete to make the slab.
To fill a 3x3x3 hole, you first calculate the volume of the hole, which is 3 feet x 3 feet x 3 feet = 27 cubic feet. A 60-pound bag of concrete typically covers about 0.45 cubic feet. Therefore, to find out how many bags are needed, divide the volume of the hole by the coverage of one bag: 27 cubic feet ÷ 0.45 cubic feet/bag ≈ 60 bags. Thus, it would take approximately 60 bags of 60-pound concrete to fill the hole.
A typical 80-pound bag of concrete mix yields about 0.6 cubic feet of concrete. A 3-yard mixer has a capacity of 81 cubic feet (3 cubic yards). To fill the mixer, you would need approximately 135 bags of 80-pound concrete mix, since 81 cubic feet divided by 0.6 cubic feet per bag equals about 135 bags.
There is no way to answer that without knowing how deep the concrete will be.