Correct me if I'm wrong but I believe the answer to the question goes like the following: 27 floors (37 offices) = 999 offices in the building
65
Exactly as in the question: 27
Exactly as in the question 27
There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.There are 28 days in 4 weeks, so if you are being asked how many days are in 4 weeks, then the answer is wrong. 27 days could be the answer to how many days are there between the first day of 4 weeks and the last day of 4 weeks.
If you answered 27 correctly and 18 incorrectly, you would have answered 60% correctly.
You can miss out 5 but then need to get all the rest correct. Also, this only works in the scoring system does not penalise wrong answers.
Correct me if I'm wrong but I believe the answer to the question goes like the following: 27 floors (37 offices) = 999 offices in the building
Provided that all the ones that you do not miss are correct, then 30% of 90 = 90*30/100 = 27.
27
The question seems wrong. Do you mean a real cube with the side length of 3 feet? The volume is 3 feet times 3 feet times 3 feet = 27 cubic feet.
% of wrong questions= 9/27 * 100%= 0.3333 * 100%= 33.33%
As of his most recent Test, in July 2010, Shahid Afridi has taken 48 wickets in 27 Test matches.
She Done Him Wrong was created on 1933-01-27.
The Wrong Car was created on 2010-09-27.
The Wrong Box was created on 1966-05-27.
27? ya.. if i am not wrong