answersLogoWhite

0

To calculate the amount of cement needed, first convert the dimensions of the sidewalk into cubic yards. The sidewalk's volume is ( \frac{4}{12} ) feet thick × 3 feet wide × 40 feet long = 40 cubic feet. Since there are 27 cubic feet in a cubic yard, the volume in cubic yards is ( \frac{40}{27} \approx 1.48 ) cubic yards. At $76 per cubic yard, the total cost would be approximately ( 1.48 \times 76 \approx 112.48 ).

User Avatar

AnswerBot

2w ago

What else can I help you with?

Related Questions

How much cement is needed to build a sidewalk that is 132 inches long 24 inches wideand 3 inches think?

Well, you make a sidewalk from concrete, not just cement. Concrete consists of cement, sand, gravel and water. You will need 5.5 cubic feet of concrete. A standard sidewalk grade of concrete would be 1 part cement, 2 parts sand, 3 parts gravel- so the sidewalk needs 0.91 cu ft of cement- about 87 pounds worth- plus sand and gravel. If you want to buy the premixed bags of concrete (like Sacrete), you will need about 17 of the 40 pounds bags. And you did not ask, but 3 inches is kind of skinny- I would go for at least a 4 inch thick sidewalk.


If a sidewalk is 110 feet long by 4 feet wide and 4 inches deep how many cubic feet of concrete will be required for the driveway?

147 cubic feet of cement are required.


How many cubic yards of cement will it take for a sidewalk 3ft wide by 4in deep by 100 ft long?

You will need 3.7 cubic yards of cement.


What is the volume of cement needed for a square slab 4 inches thick and 28 by 28 feet?

You will need at least 9.68 cubic yards of cement.


How much sand and cement you need for 2000 bricks?

To calculate the amount of sand and cement needed for 2000 bricks, you first need to determine the volume of one brick. Assuming a standard brick size of 8 inches by 4 inches by 2 inches, the volume of one brick is 64 cubic inches. For 2000 bricks, the total volume would be 128,000 cubic inches. To convert this volume to cubic feet (since sand and cement are typically measured in cubic feet), you would divide by 1728 (12x12x12). This gives you approximately 74.07 cubic feet of sand and cement needed for 2000 bricks.


How much cement for 392 square feet 4 inches deep?

1 sq. feet = 144 sq. inchesSo,392 sq. feet = 144 * 392 sq inches = 56448 sq. inchesVolume of cement needed = 56448 sq inches * 4 inch = 225792 cubic inches225792 cubic inches = 1568 cubic feet


How many tons are in 300 cubic inches?

Depends on the commodity. 300 cubic inches of mulch and 300 cubic inches of cement will not weigh the same.


How much cement is needed for slab 240 Sq ft 6 inches thick?

13 1/3 cubic yards


How many cubic yards of cement in 18 inches X 18 Inches X 6 Inches?

0.04 cubic yards.


How many cubic yards of cement in 96 inches x 18 inches x 6 inches?

0.22 cubic yards.


How many bags of cement would be needed for a cubic yard of concrete?

Forty five 80 pound bags of cement are needed to make one cubic yard of concrete.


How many cubic yards of cement will you have to use for 1248 Sq Ft?

Cubic feet needed is the thickness is 4 inches:416Cubic yards:15.3660 pound bags92580 pound bags 694