27 cubic feet = 1 cubic yard14-ft x 7-ft x 3-ft = 294 cubic feet = 108/9 cubic yards
16
Since there are 3 feet in 1 yard the distance 14 ft = 14/3 = 4.66667 yards.
14ft * 22 ft = 14*22 sq ft = 308 sq ft = 308/9 = 34.2... sq yards.
The volume of the hole is (782 x 1.5) = 1,173 cubic ft. 1 cubic yard = 27 cubic ft 1,173 cubic ft = (1,173 / 27) = 43.444 cubic yards (repeating)
27 cubic feet = 1 cubic yard14-ft x 7-ft x 3-ft = 294 cubic feet = 108/9 cubic yards
14ft * 14 ft * 6 in = 14/3 yd * 14/3 yd * 1/6 yd = 98/27 cubic yards or 3.63 cu yards (approx).
16
49 ft * 12 ft * 12 in = 49 ft * 12 ft * 1 ft = 588 cubic feet=588/27 cubic yards = 21.77... cubic yards.49 ft * 12 ft * 12 in = 49 ft * 12 ft * 1 ft = 588 cubic feet=588/27 cubic yards = 21.77... cubic yards.49 ft * 12 ft * 12 in = 49 ft * 12 ft * 1 ft = 588 cubic feet=588/27 cubic yards = 21.77... cubic yards.49 ft * 12 ft * 12 in = 49 ft * 12 ft * 1 ft = 588 cubic feet=588/27 cubic yards = 21.77... cubic yards.
Since there are 3 feet in 1 yard the distance 14 ft = 14/3 = 4.66667 yards.
55-ft x 12-ft x 18-ft = 11,880 cubic feet 27 cubic feet = 1 cubic yard 11,880 cubic feet = 440 cubic yards
14ft * 22 ft = 14*22 sq ft = 308 sq ft = 308/9 = 34.2... sq yards.
8.5 ft * 16 ft * 4.5 ft = 612 cubic ft = 612/(3*3*3) cubic yards = 22.666... cu yards
The volume of the hole is (782 x 1.5) = 1,173 cubic ft. 1 cubic yard = 27 cubic ft 1,173 cubic ft = (1,173 / 27) = 43.444 cubic yards (repeating)
Divide by 27.
(3,600 square ft) x (1 ft) = 3,600 cubic ft.1 cubic yard = 27 cubic ft3,600 cubic ft = 3,600/27 = (133 and 1/3) cubic yards
1 cubic yard = 27 cubic feet 2 cubic yards = 54 cubic feet . . . 435 cubic yards = 11,745 cubic feet