effort deviation
A budget "variance" is the difference between planned and actual performance.
In most production management systems, a "Planned" quantity and material cost is calculated based on the associated Bill of Materials (BOM) and Operatons being performed (Route) creating labor and overhead related costs. The "Actual" quantities, material costs, and labor/overhead costs are issued to a Work in Process (WIP) account and the quantities/values of the produced items are recieved from the WIP account. A variance usually occurs when there is a difference between the issued material cost plus labor and overhead and the recieved material cost of the produced item. The reasons for these variances can be differences in planned vs actual quantities, differences in system or planned cost of materials, labor, or overhead vs actual cost, or any other potential reason for an unplanned difference.
Load variance refers to the difference between the actual load (or workload) incurred and the expected or standard load that was budgeted or planned for a specific period. It is a key performance indicator used in cost accounting to assess efficiency and resource utilization within an organization. A positive load variance indicates that more resources were used than planned, while a negative load variance suggests that less was used. Analyzing load variance helps organizations identify areas for improvement and manage operational costs effectively.
Material Number,Planned Order Number
Production volume variance is calculated by taking the difference between the actual production volume and the budgeted production volume, then multiplying that difference by the standard fixed overhead rate per unit. The formula is: [ \text{Production Volume Variance} = (\text{Actual Units Produced} - \text{Budgeted Units}) \times \text{Standard Fixed Overhead Rate per Unit} ] This variance helps to assess how well the actual production aligns with planned production levels and the impact on fixed overhead costs.
The difference between the actual end date and the planned end date, expressed as a percentage of the planned duration, is calculated by first determining the actual duration of the project compared to the planned duration. This difference is then divided by the planned duration and multiplied by 100 to express it as a percentage. A positive percentage indicates the project took longer than planned, while a negative percentage suggests it was completed ahead of schedule. This metric helps in evaluating project performance and adherence to timelines.
The difference between the actual end date and the planned end date can be calculated by first determining the duration between these two dates. This difference is then expressed as a percentage of the planned duration by dividing the difference by the planned duration and multiplying by 100. For example, if the planned duration is 30 days and the actual end date is 5 days late, the percentage difference would be (5/30) * 100, which equals approximately 16.67%. This metric helps assess project performance and schedule adherence.
compare between planned and unplanned change
A reserve is a planned amount, a surplus is unplanned.
A budget "variance" is the difference between planned and actual performance.
A budget "variance" is the difference between planned and actual performance.
Absolutely no difference. The only difference may be price.
Planned Value is the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or a work breakdown structure component Earned Value is the value of completed work expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component.
Difference between the actual and planned for a effort is known as effort deviation.
Incident is not planned and means that the service is disrupted, Service Request has a planned process or procedure ready to be executed, for example password reset.
A planned end date - is an predicted estimation of when something is to cease. An actual end date - is the confirmed end.
event organizer - organises an event venue - is where an event is planned to occur