answersLogoWhite

0

because, AMERICA!

I'm a free man!

User Avatar

Wiki User

13y ago

What else can I help you with?

Continue Learning about Math & Arithmetic

When a project npv exceeds zero?

When a project's Net Present Value (NPV) exceeds zero, it indicates that the projected earnings (in present value terms) from the project surpass the expected costs, also in present value terms. This suggests that the project is likely to generate value for the investors and is considered a good investment opportunity. A positive NPV implies that the project is expected to contribute to the overall wealth of the stakeholders. Consequently, it is generally recommended to proceed with projects that have an NPV greater than zero.


If the interest rate is 5 percent what is the present value of a security that pays you 1100 next year and 1210 the year after would you be willing to pay 2310 for this security why or why not?

The NPV of this security is calculated as follows: (2310) + 1100/1.05 + 1210/1.05^2 = (164.87) Since the NPV of this investment is negative, you should not buy it.


Where can you get positive and negative wires for a class project?

You can get the positive and negative wires for a class project at a store that sells the Physics apparatus.


Which method of evaluating capital budgeting projects is generally regarded by academics as being the best single method?

The Net Present Value (NPV) method is generally regarded by academics as the best single method for evaluating capital budgeting projects. This is because NPV accounts for the time value of money, providing a clear measure of the projected profitability of a project by discounting future cash flows to their present value. A positive NPV indicates that a project is expected to generate value over its cost, guiding investment decisions effectively. Additionally, it aligns with the goal of maximizing shareholder wealth.


Response to the Caledonia Products Integrative Problem?

Response by R. NowaidResponse to the Caledonia Products Integrative ProblemProject ranking is prioritizing projects based on a project's stream of cash flow by measuring net present value (NPV), the internal rate of return (IRR), and Macaulay duration that is calibrated based on cash-flow timing. Conflict of ranking arises when managers have to make subjective decisions due to organizational goals and needs. In a mutually exclusive projects three factors remain as key ranking elements; (1) size disparity; (2) time disparity; and (3) unequal lives.Size Disparity"The size disparity problem occurs when mutually exclusive projects of unequal size are examined." In the case for Caledonia Products, Project A and B may have the same initial investment amount; however, cash inflow of Project A begins in the first year but Project B begins in the fourth year. Both projects vary on net to present value, internal rate of return, and profitability index. If size disparity causes conflicting ranking among mutually exclusive projects, then the project with the largest net present value is considered; given the fact that there would be no capital rationing. Standing alone on this criteria, Project B is more viable because total NPV of Project B is higher that Project A.Time Disparity"The time disparity problem and the conflicting rankings that accompany it result from the differing reinvestment assumptions made by the net present value and internal rate of return decision criteria." In case of Caledonia Products, total cash flow at the fifth year for Project A is $40,000 less than Project B's, NPV for Project A is less than Project B's. Project A begins cash inflow at the first year, the payback period for Project A is 3.125 years versus 4.5 years for Project B, and IRR for Project A is 18.03% versus Project B's IRR is 14.87%. Assuming that cash inflow during life of project can be reinvested, that would make Project A to be more viable.Unequal LivesUsing size and time disparities in conjunction with NPV and IRR may lead to conflicting results in analyzing mutually exclusive projects. A primary cause of conflicting ranking can be timing of the cash flows of the mutually exclusive projects. In the case of Caledonia Products, Project B may have higher total cash flow at maturity and NPV of Project B may be higher as well; however, Project A makes cash available now. Knowing cash is king, and Project A's cash inflow begins in the first year versus Project B's cash inflow that begins in the fifth year, and this feature would make Project A more attractive.AnalysisInitial net investment in Project A and Project B are equal; however, total cash flow for Project A is $40,000 less than Project B's total cash flow and NPV for Project A is less than Project B's NPV.Considering aforementioned facts one manager may consider Project B because it has greater NPV and total Project cash value; however, Project A has one main incentive, on-going cash flow throughout the Project. Project A generates continues cash flow through the life cycle of the Project; whereas, Project B requires the organization to operate without incoming cash flow until the Project is completed.Conclusively, if the organization is in need of cash to maintain profitable operation by avoiding external financing and loan, then Project A makes most sense; however, if the organization is not in need of immediate cash, then Project B is a better decision. For example, a small construction company needs continues cash inflow to prevent expensive financing of project. On the other hand, a major meatpacking firm, which does not have cash flow problem, may wait to the delivery date to collect all its funds at a greater amount.

Related Questions

Should a negative NPV project be accepted?

A negative NPV (Net Present Value) project should generally not be accepted, as it indicates that the project's expected cash flows, discounted for risk and time, do not exceed the initial investment. Accepting such a project would lead to a decrease in the firm's value and shareholder wealth. It's essential to consider alternative investments that yield a positive NPV to maximize returns. However, in certain strategic situations, a negative NPV project might be considered if it aligns with long-term goals or market positioning.


If the opportunity cost of capital for a project exceeds the projects IRR then the project has a NPV negative?

If the opportunity cost of capital for a project exceeds the Project's IRR, then the project has a(n)


When the net present value is negative the internal rate of return is the firm's cost of capital?

When the net present value (NPV) of a project is negative, it indicates that the project's expected cash flows, discounted at the firm's cost of capital, do not cover the initial investment. In this scenario, the internal rate of return (IRR) is indeed equal to the firm's cost of capital, meaning that the project is not generating sufficient returns to justify the investment. Therefore, the project would generally be considered unworthy of pursuit if the NPV is negative.


Why the NPV of a relatively long term project is more sensitive to changes in the cost of capital than is the NPV of a short term project?

due to the uncertainty


The net present value and profitability index methods to give consistent accept-reject decisions?

Yes, The PI and NPV always give the same decisions to accept or reject the projects. The Project's PI will be greater than 1.00 if the NPV is positive and PI will be less than 1.00 if the NPV is negative


When would you accept IRR and NPV?

You would accept a project if its Internal Rate of Return (IRR) exceeds the required rate of return or cost of capital, indicating that the project is expected to generate value. Additionally, if the Net Present Value (NPV) is positive, it suggests that the project's cash flows, discounted at the required rate, are greater than the initial investment, making it financially viable. In summary, accept the project if both IRR is above the threshold and NPV is positive.


For the NPV criteria a project is acceptable if the NPV is while for the profitability index a project is acceptable if the profitability index is?

less than zero, greater than the requred return


When a project npv exceeds zero?

When a project's Net Present Value (NPV) exceeds zero, it indicates that the projected earnings (in present value terms) from the project surpass the expected costs, also in present value terms. This suggests that the project is likely to generate value for the investors and is considered a good investment opportunity. A positive NPV implies that the project is expected to contribute to the overall wealth of the stakeholders. Consequently, it is generally recommended to proceed with projects that have an NPV greater than zero.


When reviewing the net present profile for a project?

When reviewing the net present value (NPV) profile for a project, it's essential to assess how changes in discount rates affect the project's NPV. A project is typically considered viable if its NPV is positive at the required rate of return. Additionally, the NPV profile can illustrate the project's sensitivity to different discount rates, helping decision-makers understand potential risks and returns. Evaluating the profile allows for informed comparisons with alternative projects or investments.


How does discount rate affect net present value?

The discount rate directly influences the net present value (NPV) by determining the present value of future cash flows. A higher discount rate reduces the present value of those cash flows, leading to a lower NPV, while a lower discount rate increases the present value and thus the NPV. If the discount rate exceeds the internal rate of return of a project, the NPV may become negative, indicating that the project may not be viable. Conversely, a lower discount rate can make an investment more attractive by increasing its NPV.


Harrys inc is considering a project that has the following cash flow and wacc data what is the projects npv?

Harry\'s Inc. is considering a project that has the following cash flow and WACC data. What is the project\'s NPV? Note that if a project\'s projected NPV is negative, it should be rejected. WACC: 14.75% Year 0 1 2 3 4 5 Cash flows -$1,000 $300 $300 $300 $300 $300 A. $10.58 B. $13.02 C. $11.63 D. $9.07 E. $10.12 You can also get answer on onlinesolutionproviders com thanks


IRR VS NPV?

IRR: Internal rate return NPV: Net present value Both are measure of the viability of a project(s) You can have multiple IRR (because of discontinued cash flows) but you always have one NPV.