Job workers using this formula as given :-
total hrs. in Single pass (Single cut)=Total Path length x job thickness / 1500
total hrs. in Double pass (Double cut)=Total Path length x job thickness / 1200
total hrs. in Triple pass (Triple cut)=Total Path length x job thickness / 900
total hrs. in Four pass (Four cut)=Total Path length x job thickness / 600
and the Rates are Rs.200.00/hr to Rs.250.00/hr.
Either calculate the distance travelled (in miles) and divide by the total time (in hours) taken to undertake the journey or calculate in other units and carry out a conversion.
Distance = Rate * Time or, for our purposes Time = Distance/Rate Time = 280 km/70 kmh = 4 hours -------------
Divide 245 miles by 3.5 hours.That gives 245/3.5 = [you can work this out] miles per hour.
how much be 7 dollars a hour for one week answer please
It is 36.25 for the week.
in a normal 40 hour work week $/hour x 40 hours/week x 52 weeks/year Try the link below to experiment on some numbers
Usually one hour per hour.
If you are paid by the hour at a uniform rate, simply multiply the hours worked by therate per hour. If you are paid different rates, say for overtime or hazardous work,you would have to multiply each rate by the number of hours worked at that rate and add these to get the total gross pay.1916.67
The standard answer is to divide the annual rate by 2000 to get an hourly rate. Assumes a 40 hour work week and a 50 week work year$49,000 / 2000 hours = $24.50/hour
A machine hour rate is the cost of one machine working for one hour. This is used in calculating overhead costs to work in process as opposed to using labor hours.
assuming you work a 40 hour week, including holidays, $8.17/hour.
Assuming you work a 40 hour week - 9.615 per hour.
Overtime is work done outside your normal daily hours. If you normally work an eight hour day, but work an extra hour one day. That extra hour is overtime, and overtime is often paid at a higher rate.
It's roughly $22.12 an hour. Take the annual rate and divide by 2080 (the number of hours in a work year) and you will get the hourly rate.
The speed at which work is done is called the work rate. It is measured as the amount of work completed in a given amount of time, typically expressed as units of work per unit of time (e.g. miles per hour, tasks per hour). A higher work rate indicates that work is being done more quickly.
290/25 = 11.60 per hour
I believe you are thinking of a watt perr hour or more commonly used is a kilo-watt-hour - that's the amount of power used in an hour, not exactly how much work is done however.