An acre is 43650 sq ft.
In 2.12 acres, there are 92347.2 sq ft.
If you need to dig out 1 foot over the entire property, you will be removing 92347.2 cubic feet of dirt. Divide by 27 (cubic feet in a cubic yard) to convert the volume to 3420.3 cubic yards.
If an average commercial dump truck holds 10 to 14 cubic feet of dirt, that translates to anywhere from 244 to 342 truckloads of dirt to haul away.
Chat with our AI personalities
A paver, or paving stone, is ... well, "paving stone" ought to be enough of a definition. They're usually made of clay (like bricks) or cement.
An additive process in art means adding material to the piece. Building a sculpture from clay is additive because you add clay. A subtractive process means subtracting material away from the piece. Carving a stone statue is subtractive because you take away stone.
16
If you're good with your hands, you can make a cube out of one ball of clay,or a cubical frame out of one straw cut into 12 equal pieces.Ohhhh wait ! Now I see what you're driving at. Maybe the little clay balls arewhat you use at the corners to stick the pieces of straw together. OK.You still need 12 pieces of straw all the same length, and then you need eightballs of clay to stick the corners together and make a cube.I apologize for giving you the answer. Now you'll never think it through on your own,and you'll never understand why that's the answer.
Clay