Each person averages 1/56th of a ditch (0.01786) per day.

*It would take 112 people to complete the ditch in half a day.*

User Avatar

Wiki User

10y ago

What else can I help you with?

Related Questions

It takes 7 people 8 days to dig a ditch how many people would it take to dig the ditch in one half day?

112 people are needed


If it takes 7 people 8 days to dig a ditch how many people would it take to dig the ditch in 12 day If it takes 7 people 8 days to dig a ditch how many people would it take to dig the ditch in 12 day?

To find out how many people are needed to dig the ditch in 12 days, we first calculate the total work needed in terms of person-days. The total work is 7 people × 8 days = 56 person-days. If the ditch needs to be dug in 12 days, we divide the total work by the number of days: 56 person-days ÷ 12 days = approximately 4.67 people. Since you can't have a fraction of a person, you would need at least 5 people to complete the work in 12 days.


If it takes 7 people 8 days to dig a ditch how many people would it take to dig the ditch in 12 day?

That my friend would take 11 people to dig the ditch. thanku pls. X Wouldn't it be 3 to 4 people? 3.5 to be exact.


If it takes 7 people 8 days to dig a ditch how many people would it take to dig a ditch in 12 a day?

That my friend would take 11 people to dig the ditch. thanku pls. X Wouldn't it be 3 to 4 people? 3.5 to be exact.


How many people does it take to dig a ditch in a half day if it takes 7 people 8 days to dig a ditch?

If 7 people can dig a ditch in 8 days, that means the total work required is 7 people × 8 days = 56 person-days. To determine how many people are needed to complete the task in half a day (0.5 days), you would divide the total person-days by 0.5 days: 56 person-days ÷ 0.5 days = 112 people. Therefore, it would take 112 people to dig the ditch in half a day.


If it takes 7 people to dig a ditch in 8 days how many people would it take to dig a ditch in a half of a day?

To find out how many people it would take to dig the ditch in half a day, we first calculate the total amount of work in "person-days." If 7 people can complete the work in 8 days, that amounts to 7 people × 8 days = 56 person-days. To complete the work in half a day, you would need 56 person-days ÷ 0.5 days = 112 people. Therefore, it would take 112 people to dig the ditch in half a day.


If it takes 7 people 8 days to dig a ditch how many people would it take to dig the ditch in 12 days?

Assuming the linear relationship holds true, it would take 4.67 people to dig the ditch. Since there is no such thing as 0.67 of a person, the answer should be 5 people.


If it takes 2 people to dig a 20 by 30 ditch how long does it take 4 people?

45 minutes


anyone can dig a ditch but it takes a real man to?

get an Education


If it takes 10 people 10 days to dig a hole how long will it take 5 people to dig half a hole?

5 days


Ten people take 4 days dig a hole,how long it takes 8 people?

2 days


If it takes 8 workers 8 days to dig a trench how long will it take 4 workers to dig half a trench?

Eight days.