If most of the off-cuts are also used then you will need 315 slabs. Otherwise you will need a lot more.
Area to be covered = 12ft * 14ft = 3657.6 mm * 4267.2 mm = 15,607,711 mm2 Area of each slab = 900mm * 600 mm = 540,000 mm2. So, number of slabs required = 28.9 ie 29 slabs. That is the mathematical answer. It assumes that almost all offcuts can be used up and that there are no breakages. In "real life" it is advisable to allow 5-10% for wastage.
The answer will depend on the size of the patio slabs.
The answer will vary slightly depending on assumptions: will the slabs have a space between them, and will you be cutting the slabs to fill fractions. 21 feet is equal to 14.2 of the 450 mm slabs. 19 feet is equal to 12.9 of the slabs. To complete the rectangular area, 14.2 x 12.9 = 183 slabs.
20 I believe
You will need 63 44cm x 44cm slabs to cover that area.
140
To determine how many 450mm x 450mm slabs are needed to cover a 5ft x 4ft area, first convert the dimensions to millimeters: 5ft is approximately 1524mm and 4ft is approximately 1219mm. The area of the space is 1524mm x 1219mm = 1,860,756 mm². Each slab covers an area of 450mm x 450mm = 202,500 mm². Dividing the total area by the area of one slab gives you approximately 9.2, so you will need 10 slabs to cover the area completely.
To determine how many 400x400 mm slabs fit in a square meter, first convert the dimensions of the slab to meters: 400 mm is 0.4 m. The area of one slab is 0.4 m x 0.4 m = 0.16 m². Since one square meter equals 1 m², you can fit 1 m² / 0.16 m² = 6.25 slabs. Therefore, you can fit 6 slabs, with a little area left over.
150 sq ft = 13.94 sq metres, approx. That area would require 68.8 or 69 slabs. However, this assumes that the area to be covered is "well-behaved" and that wastage is kept to a minimum.
220 should do it.
40 slabs
42 slabs...