Area to be covered = 12ft * 14ft = 3657.6 mm * 4267.2 mm = 15,607,711 mm2
Area of each slab = 900mm * 600 mm = 540,000 mm2.
So, number of slabs required = 28.9 ie 29 slabs.
That is the mathematical answer. It assumes that almost all offcuts can be used up and that there are no breakages. In "real life" it is advisable to allow 5-10% for wastage.
150 sq ft = 13.94 sq metres, approx. That area would require 68.8 or 69 slabs. However, this assumes that the area to be covered is "well-behaved" and that wastage is kept to a minimum.
Ah, what a lovely question! To find out how many 450x450 slabs are in a square meter, we need to do a little math dance. Since each slab covers an area of 0.45m x 0.45m, we can fit approximately 4 slabs (1/0.45) in one square meter. So, you can joyfully place 4 of these delightful slabs in a square meter of space. Happy painting!
Depends on the linear dimensions of both the slabs and the ground.
305.56
You will need a minimum of 153 slabs. However, that answer assumes that the area to be covered is "well behaved" and that you are happy to use offcuts and chippings so that part of the area will look like a mosaic. If these conditions are not met, you should consider getting 5% extra slabs.If, for example, the 55 sq metre area is in the form of a rectangle which is 550 mm wide and 100 metres long it may be easier to cover it using 167 trimmed slabs in a long line rather than use offcuts which are 5 mm wide.
If most of the off-cuts are also used then you will need 315 slabs. Otherwise you will need a lot more.
The answer will depend on the size of the patio slabs.
The answer will vary slightly depending on assumptions: will the slabs have a space between them, and will you be cutting the slabs to fill fractions. 21 feet is equal to 14.2 of the 450 mm slabs. 19 feet is equal to 12.9 of the slabs. To complete the rectangular area, 14.2 x 12.9 = 183 slabs.
12' x 14' is equal to: 15.61 square meters.
To determine how many paving slabs are needed for a 14ft by 14ft area, first calculate the total area: 14ft x 14ft = 196 square feet. If each paving slab covers a specific area (for example, a standard slab is 2ft x 2ft, which is 4 square feet), divide the total area by the area of one slab. For 2ft by 2ft slabs, you would need 196 / 4 = 49 slabs. Adjust the calculation based on the actual size of the slabs used.
20 I believe
You will need 63 44cm x 44cm slabs to cover that area.
140
First, convert the area of 12x24 feet to square meters: 12 feet is approximately 3.66 meters and 24 feet is about 7.32 meters, giving an area of about 26.8 square meters. The area of one 600m x 600m slab is 0.36 square meters. To find how many slabs are needed, divide the total area by the area of one slab: 26.8 ÷ 0.36 ≈ 74.4. Therefore, you would need 75 slabs to cover the area.
To cover a 24ft by 24ft area, you first calculate the total area, which is 24ft x 24ft = 576 square feet. Each 3ft by 2ft paving slab has an area of 6 square feet (3ft x 2ft). To find the number of slabs needed, divide the total area by the area of one slab: 576 square feet ÷ 6 square feet per slab = 96 slabs. Therefore, you would need 96 slabs to cover the area.
To determine how many 450mm x 450mm slabs are needed for a 30m² area, first convert the slab dimensions to square meters. Each slab is 0.45m x 0.45m, which equals 0.2025m². Next, divide the total area (30m²) by the area of one slab (0.2025m²): 30 ÷ 0.2025 ≈ 148.15. Therefore, you would need 149 slabs to cover the area, rounding up to the nearest whole slab.
To determine how many 400mm x 400mm slabs are needed to cover an area of 6ft x 8ft, first convert the dimensions to millimeters: 6ft is approximately 1829mm and 8ft is about 2438mm. The area to be covered is 1829mm x 2438mm = 4,467,642mm². Each slab covers an area of 400mm x 400mm = 160,000mm². Dividing the total area by the area of one slab gives approximately 28 slabs needed (4,467,642mm² ÷ 160,000mm² ≈ 27.92).