of men is inversely related to # of days:
42 men * 15 days = x men * 21 days
x = (15*42) / 21 = 30 men
Answer: 30 men
In one day A does 10% of the work and B does 12½%, so after A's 6 days he has done 60%, leaving 40% for B who will need three-and-a-fifth days to complete the work.
1 man would take 80 days to complete the work, so 1 man in 1 day would complete 1/80 of the work. 1 child would take 160 days to complete the work, so 1 child in one day would complete 1/160 of the work. In 1 day, 5 men and 10 children could do 5/80 + 10/160 = 1/16 +1/16 = 1/8 of the work. It would take them 8 days to do the job.
14 days - 4 hrs. Purna.
1 day = 24 hours. You now have all the information required to work out, for yourself, the answer to this and similar questions.
1 day = 24 hours. You now have all the information required to work out, for yourself, the answer to this and similar questions.
4 men are required
2 Days. 2 people x 5 days = 10 days of work. 10 days / 5 people=2 days
In one day A does 10% of the work and B does 12½%, so after A's 6 days he has done 60%, leaving 40% for B who will need three-and-a-fifth days to complete the work.
It might have been possible to answer the question is you had had the time to complete the question!
1 man would take 80 days to complete the work, so 1 man in 1 day would complete 1/80 of the work. 1 child would take 160 days to complete the work, so 1 child in one day would complete 1/160 of the work. In 1 day, 5 men and 10 children could do 5/80 + 10/160 = 1/16 +1/16 = 1/8 of the work. It would take them 8 days to do the job.
when ever need in a court of law
14 days - 4 hrs. Purna.
If the work that is required is the same amount, then the work to people ratio is 5:20. To get to 1 hour, you need to divide the amount of time by 5. Since you are going to need more people to complete the work, you then multiply the number of people by 5, and 20*5=100. Therefore, you need 100 people to complete the work in 1 hour.
The Number of men required is 160 Explanation: Let no. of men = m1 = 10 Let no. of days required = d1 = 8 Let no. of men required to finish the work in 1/2 days = m2 Let no of days required for m2 men = 1/2 Now we have to find the no. of men required to complete the work in 1/2 day so the calculation will be, m1d1 = m2d2 (10)(8) = m2(1/2) 80 = m2(1/2) [ By taking the dividend 2 left side it will go into multiple ] 80 x 2 = m2 160 = m2 Therefore, Number of men required to finish the work in 1/2 day is **160 men**
none, you work when you want.
Advantages: -make work much more easier to complete -make work faster to complete -less energy required -less exerted force required Disadvantages: -may malfunction and corrupt the entire system
12 days