There are twenty-seven cubic feet in a cubic yard. So, you'd have 27,000 cubic feet in 1000 cubic yards. Assuming you leave each cubic foot intact and since there are 43,560 square feet in an acre then you'd be able to cover over half an acre. At only 6" deep you'd cover over an acre.

User Avatar

Wiki User

โˆ™ 15y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: How much does 1000 cubic yards of fill dirt cover?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

Will 6 yards of dirt cover 70 square feet of land?

6 cubic yards of dirt will cover 70 sq ft ... 2 ft 3 3/4 inches deep


How much dirt is required to cover 1 acre 6 inches deep?

806.66 Cubic Yards


How much dirt is 18 tons?

Dirt has varying densities, but on average, 18 tons of dirt would fill about 12 cubic yards.


How many yards of dirt is 14 cubic feet?

14 cubic feet = 0.518 cubic yards


How many cubic yards of dirt to cover 3600 square feet to a depth of two inches?

22.22 cu yd


How many cubic feet in 7 yards of dirt?

There are 189 cubic feet in 7 yards of dirt. This can be calculated by multiplying the number of cubic yards by 27, since there are 27 cubic feet in a cubic yard.


How do you calculate the amount of topsoil that is needed to cover 2400 sq ft of dirt with 2 inches of topsoilas measured in yards... I would guess they mean cubic yards?

A cubic yard of stone that is 4" thick would cover 9 square yards or 81 square feet. If you need to cover 7000 sq. ft., you would need roughly 86.5 cubic yards. That's a lot of rock.


How many Yards of dirt do you need to cover 225 square Feet one inch thick?

0.69444 cubic yard (rounded)


If you figured an area is 600 cubic yards how many yards of dirt do you need to fill that area?

To calculate the volume of dirt needed to fill the area, you would need to know the depth of the area in yards. If the depth is 3 yards, then you would need 1800 yards of dirt (600 cubic yards รท 3 yards). If the depth is 1 yard, then you would need 600 yards of dirt.


How do you calculate the amount of stone that is needed to cover 7000 sq ft of dirt with 4 inches of stone as measured in yards... I would guess they mean cubic yards?

Well, you would take the 7000 square feet of dirt and multiply it by the four inches of stone to get the 28000 cubic yards of stone. (28000 yds³)


A hole that is 2 yards wide3 yards long and 1 yard deep How many cubic feet of dirt are in it?

None because it's a hole but 6 cubic yards of dirt will fill it up.


How many cubic yards of dirt are required to fill an area 10ftx10ftx4?

133.33 cubic yards, that's 400 feet