500 pounds cement, 1500 pounds sand, 1600 pounds gravel. Mix with 32 gallons water
15 milligrams
Figure about 1/2 cubic foot per 60 lb bag. The basic formula is to use equal amounts of cement, sand, and gravel. There are 27 cubic yards per cubic foot. It depends upon how thick you are planning to pour the concrete. For one foot thick, you would need 9 cubic feet of concrete. For 6" thick, you would need 4 1/2 cubic feet. I'll give you the answers for 1 ft thick and for 6" thick. For 1 foot thick, you need 9 cubic feet at 1/2 cubic foot per 60 lb bag equals 18-60 lb bags. That's six 60 lb bags of concrete, plus six 60 lb bags of sand, plus 360 lbs of gravel. For 6 inches thick, divide each of these by 2 to give 3-60 lb bags of concrete, 3-60 lb bags of sand, plus 180 lbs of gravel.
Well, darling, if you want a concrete slab that's 5 inches thick, you'll need about 0.012 cubic meters of cement and 0.06 cubic meters of sand per square meter. Just make sure you mix it well and pour it like a boss. Good luck with your project, sugar!
7 bags cement
This depends on the size of gravel, the water content of the gravel, and the material composition of the rock used to make the gravel. Typically 1 cu.yd. of gravel wieghs 3000 lb.
Concrete actually contains cement as well as sand and gravel. We say "cement concrete" because cement is an ingredient in concrete. And because the cement is what binds together the sand and gravel that make up the concrete.
Concrete.
Concrete is what you make a sidewalk from. To make concrete, you mix Portland cement, sand, gravel (aggregate) and water. The cement holds the aggregate together.
Cement is mixed with sand, gravel, and water to make concrete. Sand and gravel act as the aggregate to provide strength and structure, while water is crucial for hydration of the cement to form a solid material.
Forty five 80 pound bags of cement are needed to make one cubic yard of concrete.
Cement and aggregates (such as sand or gravel) are mixed with water to make concrete. Cement acts as the binder, while aggregates provide the structural strength of the concrete mixture.
just get a gravel, sand, and cement and then mix it with a little amount of water.
To make 1 cubic yard of concrete, you typically need about 1.5 to 2 sacks (94-pound bags) of Portland cement, which is a key ingredient. The amount of navvy jack, or gravel, required can vary based on the desired mix ratio, but generally, you would need around 1.5 cubic yards of gravel. The standard concrete mix ratio is usually 1 part cement, 2 parts sand, and 3 parts gravel. Therefore, the specific quantity of navvy jack will depend on the total volume of aggregates used in the mix.
15 milligrams
A concrete mixture of sand, cement, and small gravel is used to make the concrete from which the tubular concrete pipe is made. The pipe is made of concrete.
Both glass and concrete contain sand. Sand is melted to make glass. It is mixed with aggregate (gravel) portland cement and water to make concrete.
The grey powder mixed with sand and gravel to make concrete is called cement. Specifically, it is often Portland cement, which is the most common type used in construction. When combined with water, cement undergoes a chemical reaction that allows it to harden and bind the aggregates together, forming solid concrete.