It depends on the Grade of Concrete.

general grades are M15, M20, M25 etc.

here are the nos. of bag required

-------------------Bag for 1 cum---------------Bag for 5 cum

M15------------------- 6.4----------------------------32

M20-------------------- 8-----------------------------40

M25--------------------12----------------------------60

User Avatar

Wiki User

13y ago

What else can I help you with?

Continue Learning about Math & Arithmetic

How many number of cement needed to get one cubic meter of concrete?

30


How do you calculate number of bags of cement required for 1 cubic meter of m15 grade cement concrete as per Indian standard code?

To calculate the number of bags of cement required for 1 cubic meter of M15 grade concrete, first determine the mix ratio, which is typically 1:2:4 (Cement:Sand:Aggregate). For M15 concrete, approximately 1 part cement is needed for every 7.5 parts of total volume (1 + 2 + 4 = 7). Given that one bag of cement weighs 50 kg and has a volume of about 0.035 cubic meters, you would need around 7.5 bags of cement for 1 cubic meter of M15 concrete.


How do you calculate the cement ratio and number of bags of cement for 1cumic?

To calculate the cement ratio for 1 cubic meter (cumic) of concrete, you first need to determine the mix ratio (e.g., 1:2:4 for cement, sand, and aggregate). The total parts of the mix are summed, and the volume of cement is calculated based on the proportion of the mix. For example, in a 1:2:4 mix, the total parts are 1 + 2 + 4 = 7. The volume of cement needed is then (1/7) × 1 cubic meter, which equals approximately 0.143 cubic meters. Given that one bag of cement typically weighs 50 kg and occupies about 0.035 cubic meters, you would divide the volume of cement by the volume per bag to find the number of bags: 0.143 / 0.035 ≈ 4.1 bags.


The equation below shows the rule for the function VS use it to find the number of cubic meters of cement needed to make a pyramid with four metered sides round your answer to the nearest hundredth?

36


How much cement is needed for sidewalk that is 4 inches thick 3 feet wide and 40 feet long the cement is sold for 76 per cubic yard?

To calculate the amount of cement needed, first convert the dimensions of the sidewalk into cubic yards. The sidewalk's volume is ( \frac{4}{12} ) feet thick × 3 feet wide × 40 feet long = 40 cubic feet. Since there are 27 cubic feet in a cubic yard, the volume in cubic yards is ( \frac{40}{27} \approx 1.48 ) cubic yards. At $76 per cubic yard, the total cost would be approximately ( 1.48 \times 76 \approx 112.48 ).