T = Ta/Td

Where

T = Takt time, e.g. [minutes of work / unit produced]

Ta = Net Time available to work, e.g. [minutes of work / day]

Td = Time demand (customer demand), e.g. [units required / day]

User Avatar

Wiki User

โˆ™ 15y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What is the formula to work out takt time?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

What is the takt time used for?

Takt time comes from the german word Taktzeit. Takzeit means cycle time. Takt time is used for industrial manufacturing lines. Takt time is put into a mathematical expression to express the cycle time.


What is the best definition of Takt time?

Takt Time is the pace at which your customers demand what you provide them


What does takt stand for?

Takt Time is the pace at which your customers demand what you provide them


What is the difference between takt time and cycle time?

cycle time is a time between two measuring points and TAKT time is a rate or frequent.


What is takt time used in Lean manufacturing?

Time Available divided by customer demands


How did they find assembly line balancing?

1) First you need to construct a precedence chart of tasks. For example: A ----> B ----> C ----> D 2) Next, do time study to determine how much time required to perform each task. A (4 mins) ----> B (2 mins) ----> C (2 mins) ----> D (2 mins) 3) Find the takt time. Takt time = available production time per day/customer demand per day 4) Calculate the minimum number of workstations required, given the task times above. Below is the formula: Min # workstations = Total time for tasks divided by takt time Hope it helps!


Manufacturing cycle time?

Mechanical engineers aren't the best source for answering manufacturing questions. Takt time is a function of total available time for production and production demand. Example: If you have 100 minutes available for production per day and your need is to produce 100 pieces per day, your takt time would be 1 minute. If you need 200 pieces per day, then your takt time would be .5 minutes. In other words, you need to produce a part every 30 seconds to make the plan.


If the formula to calculate work is distance divided by time how do you apply the formula?

You would have a very tough time, because that isn't the formula to calculate work. (distance) divided by (time) is the formula to calculate speed. The formula to calculate work is: (force) multiplied by (distance).


What is formula of power?

the formula for power is work/time.


What formula relates work and power?

The formula that relates work and power is: Power = Work / Time. Power is the rate at which work is done, which is the amount of work done divided by the time it takes to do that work.


What is the formula for measuring the rate of work?

The formula for measuring the rate of work is: Work = Force ร— Distance รท Time. This formula takes into account the force applied, the distance over which the force is applied, and the time taken to complete the work.


When calculating power you should use the formula P divided by . IN this formula P stands for power stands for work and for time.?

The correct formula for calculating power is P = W/t, where P is power, W is work, and t is time. Power is a measure of how much work is done in a given amount of time, so dividing work by time gives you the power value.