8
7 cement bags per 1 cubic meter of concrete......
According to Blue Circle it takes 108 bags of concrete to get a cubic meter
15 milligrams
One cubic meter of concrete is equal to 1.308 cubic yards of concrete. If there are 5 1/2 bags of cement in 1 cubic yard of concrete, there would be 7.2 bags in 1 cubic meter of concrete. These are the 94 pound bags of portland cement or roughly 40kg bags so figure 8 bags total. Some will be left over
one bag
7 cement bags per 1 cubic meter of concrete......
Forty five 80 pound bags of cement are needed to make one cubic yard of concrete.
According to Blue Circle it takes 108 bags of concrete to get a cubic meter
15 milligrams
One cubic meter of concrete is equal to 1.308 cubic yards of concrete. If there are 5 1/2 bags of cement in 1 cubic yard of concrete, there would be 7.2 bags in 1 cubic meter of concrete. These are the 94 pound bags of portland cement or roughly 40kg bags so figure 8 bags total. Some will be left over
108
one bag
4000PSI, 12bags, .5cum3sand 1cu.m3 gravel
In an M15 grade nominal mix, the typical ratio is 1:2:4 (cement:sand:aggregate). For 1 cubic meter of concrete, you would generally need about 7 bags of cement, as one bag of cement weighs 50 kg and approximately 0.035 cubic meters of cement is used. Therefore, the total quantity of cement needed for 1 cubic meter of M15 concrete is around 350 kg, which translates to about 7 bags.
4.4 bags
To make 1 cubic meter of concrete, you typically need about 350 to 400 kg of cement, depending on the mix design. Given that a standard 20 kg bag of cement contains 20 kg, you would require approximately 17 to 20 bags of cement to achieve 1 cubic meter of concrete. Always consider the specific mix proportions and requirements for your project, as these can vary.
To calculate the number of bags of cement needed for a slab measuring 14 feet by 11 feet and 4 inches thick, first convert the dimensions to cubic yards. The volume is approximately 4.58 cubic yards. Generally, one cubic yard of concrete requires about 5 to 6 bags of Portland cement, so you would need approximately 23 to 27 bags of cement for this slab.