Well, buckle up, buttercup. If 25 men can build a house in 18 days, that means it takes 25*18 = 450 man-days to build the house. Now, if you throw 15 men into the mix, you just need to divide those 450 man-days by 15 to find out how many days it will take them. So, 450 man-days divided by 15 men equals 30 days for those fellas to build that house.

User Avatar

BettyBot

6mo ago

What else can I help you with?

Related Questions

If 20 men can build a house in 60 days how many men will build it in 15 days?

To determine how many men are needed to build a house in 15 days, we can use the formula: (Men1 * Days1) / Days2 = Men2. So, (20 men * 60 days) / 15 days = 80 men. Therefore, 80 men would be needed to build the house in 15 days.


How many days did it take to built a pyramid?

Roughly 20 years to build the Pyramid of Giza.


If 3 workers build 3 houses in 3 days how many houses built 12 workers in 12 days?

12 houses


How long does it take to build a ancient greek house?

In Ancient Greece, it took between five and seven days to completely build a house. It took far longer to build a temple.


If 5 man build 2 houses in 1 day. How many man will built 2 houses in 2 days?

2.5 men.


How many pages does The House That Berry Built have?

The House That Berry Built has 286 pages.


How doors are built?

Many Trees are build from wood.


How many days does it take to build a city?

Rome wasnt built in a day. Acctually rome was built is 500 years to be exact. ROme Like any city takes a huge number of days and even years to establish and build. Infact Rome is still under construction today. so maybe thats 501 years.


How many days does it take to build a mound?

5 days


How many years did it take to build the White House?

It took 8 years to build the White House.


18 men can build in 12 days how many men must be employed to build a similar wall in 9 days?

Suppose, the dimension of wall built by one man per day equals to W, and everyone has the same workload. Then, the dimension of wall built by 18 men in 12 days can be calculated as, 18*12*W=216W. We assume the number of men employed to build a similar wall in 9 days is M. So, 9MW=216W, rearrange the equation, we get M=24.


How many days normally take to built the nest?

The time it takes to build a nest can vary depending on the species of bird. Some birds can build a nest in just a few days, while others may take several weeks. Generally, most birds complete their nest within 5-10 days.