To determine how many men are needed to build a house in 15 days, we can use the formula: (Men1 * Days1) / Days2 = Men2. So, (20 men * 60 days) / 15 days = 80 men. Therefore, 80 men would be needed to build the house in 15 days.
4 men are required
6 men took 20 days so it is 120 man-days worth of work. 4 men will take 120/4 = 30 days to do the work.
15 days
a man is building a fence for 3 days if 3 men build the fence, how many days can they build it? solution: 1x3=3/3= 1the answer is 1!===There's no such commonly recognised thing as 'indirect proportion'. If you mean Inverse Proportion, this is when one quantity decreases as another increases by the same factor.As an example, the time it takes to run 100 m is inversely proportional to the speed you run at - if you double your speed, it takes you half as long.Many maths problems run along the lines of "If it takes three men four days to build a wall, how long will it take five men to build the same wall?". This is inverse proportion. As you increase the number of men by a factor of 5/3, you decrease the time taken by a factor of 5/3, so the answer here is 2.4 days.I hope that helps!
Four men can paint eight houses in two days.How many days does it take a man to paint a house ?Note: This problem does not equal 1, but its solution does.
Well, buckle up, buttercup. If 25 men can build a house in 18 days, that means it takes 25*18 = 450 man-days to build the house. Now, if you throw 15 men into the mix, you just need to divide those 450 man-days by 15 to find out how many days it will take them. So, 450 man-days divided by 15 men equals 30 days for those fellas to build that house.
75 / 5 = 15 days for 12 men to build one house. 15x12 = 180 days for 1 man to build 1 house. 180 x 7 = 1260 days for 1 man to build 7 houses. 1260 / 20 = 61 days for 20 men to build 7 houses.
35 days
1 wall = 5 men X 8 days = 40 man days 40 man days / 3 men = (40/3) days = 13 1/3 days
4 days
Suppose, the dimension of wall built by one man per day equals to W, and everyone has the same workload. Then, the dimension of wall built by 18 men in 12 days can be calculated as, 18*12*W=216W. We assume the number of men employed to build a similar wall in 9 days is M. So, 9MW=216W, rearrange the equation, we get M=24.
10
Building 5 houses takes 12 x 75 ie 900 man-days. 20 men will thus take 900/20 ie 45 days.
2.5 men.
It takes 100 man-days, so three men would take 33 and a third days and 8 men 12½ days. Working together the 3 men and 8 men would take 100/11 or 9 and a ninth days