15' x 15' (225 square feet) = 25 square yards.
45 x 66 = 2970 ft2 15 yards = 45 feet 22 yards = 66 feet
25 square yards.
22.5
15' x 17' (255 square feet) = 28.3 square yards.
12*15*.33333= 60 cubic feet. 60 cubic feet/27 cubic feet per cubic yard = 2.222 cubic yards
To convert the measurements to yards: 270 feet = 90 yards, 470 feet = 156.67 yards, and 15 feet = 5 yards. Multiply the three dimensions to find the volume in cubic yards: 90 yards x 156.67 yards x 5 yards = 70350 cubic yards of earth.
To convert the dimensions to yards, we first convert inches to yards by dividing by 36 (since 1 yard = 36 inches). Then we multiply the dimensions to get the volume in cubic yards. 25 feet = 25 feet 13 feet = 13 feet 4 inches = 4/36 yards = 1/9 yards Volume = 25 * 13 * 1/9 = 36.111 cubic yards (rounded to 3 decimal places).
Multiply (acre-feet) by (1,613 and 1/3) to get (cubic yards). 3 acre-feet = 4,840 cubic yards. Multiply (cubic yards) by (0.00062) to get (acre-feet). 24,200 cubic yards = 15 acre-feet
To convert feet to yards, you need to know that 1 yard is equal to 3 feet. To convert 15 feet to yards, you would divide 15 by 3, which equals 5 yards. Therefore, 15 feet is equivalent to 5 yards.
110 cubic yards (rounded)
for a concrete order, I would calculate the cubic footage first: 15 X 31 X 0.33 (4 inches) =153.45 cubic feet. there are 27 cubic feet in one cubic yard, so 154 (round up in construction--believe me..) again 154 divide by 27 is a concrete order of 5.703 cubic yards. cheers mate!
3 Beds x 5' x 15' x 9" = convert all measurements to yards: 3 Beds x (5/3) yards x (15/3) yards x (9/36) yards= 3 Beds x 1.6667 yards x 5 yards x .25 yards = 6.25 cubic yards.
1 yard = 3 feet. Thus, to convert from yards to feet, you multiply by 3.
It is: 15/3*20/3*8/3 = 88.89 cubic yards rounded to two decimal places
There are 5 yards in 15 feet of fabric. To convert feet to yards, divide the number of feet by 3 because 1 yard is equal to 3 feet.
Yards are for measuring length not volume. Cubic yards required will be as follows: 1 cubic yard = 3 feet x 3 feet x 3 feet = 27 cubic feet Your concrete pad is 30ft x 40ft x 0.3333ft (4 inches assumed) = 400 cubic feet 400 divided by 27 = 14.8148 cubic yards required