answersLogoWhite

0

To produce 1 cubic meter of concrete, the typical mix design requires approximately 1.5 to 2 cubic meters of sand and aggregate combined, depending on the specific mix ratio. A common mix ratio is 1 part cement, 2 parts sand, and 3 parts aggregate, which translates to about 0.5 cubic meters of sand and 0.75 cubic meters of aggregate. However, the exact quantities can vary based on the desired strength and application of the concrete. Always refer to a specific mix design for precise measurements.

User Avatar

AnswerBot

2mo ago

What else can I help you with?

Related Questions

What is weight of aggregate in 1 cubic meter of concrete?

One ton


How much sand and aggregate required 1 cubic meter of plain concrete cement?

For plain cement concrete, the aggregate used is of size 20 mm. For RCC structures, it is 40mm and for roads, it is 80mm


How much cement required 1 cubic meter m10 grade concrete?

To calculate the amount of cement required for 1 cubic meter of M10 grade concrete, which has a mix ratio of 1:3:6 (Cement: Sand: Aggregate), you can use the following formula. The total parts of the mix are 1 + 3 + 6 = 10 parts. For 1 cubic meter, the volume of cement required is approximately 1/10 of the total volume, which is about 0.1 cubic meters. Given that the density of cement is around 1440 kg/m³, you would need approximately 144 kg of cement for 1 cubic meter of M10 concrete.


How much water is REQUIRED in one cubic meter of concrete?

12L


How do you mix 1 cubic meter of concrete?

A typical mixture of concrete will be 10 to 15% cement, 60 to 75% aggregate, and 15 to 20% water.


How many tons of stone does a cubic meter of concrete has?

A cubic meter of concrete typically weighs about 2.4 tons, which includes the weight of the aggregate (stone), cement, water, and any additives. The stone itself usually represents a significant portion of this weight, but the exact amount can vary depending on the mix design. Generally, the aggregate portion can be around 1.5 to 1.7 tons per cubic meter.


How many cubic meter of bricki n a cubic meter concrete?

I'm assuming by bricki you mean aggregate? There are several different mixes of concrete that yield different strengths. One of the more common mixes is a 3/2/1 mix this combines 3 parts aggregate (crushed stone), 2 parts sand and 1 part portland cement. with this mixture to make 1 cubic meter of concrete you will need almost 1/2 cubic meter of aggregate, 1/3 cubic meter sand and 1/6 cubic meter portland cement mixed with about 75 liters of water. Different mixes use varying amounts of stone though the sand and cement mixture stays between 1 1/2 : 1 to 2:1


How much aggregate cement sand is required to make 1 cube concrete?

To make 1 cubic meter of concrete, the typical mix ratio for a standard concrete is about 1 part cement, 2 parts sand, and 3 parts aggregate (1:2:3). This means you would need approximately 350 kg of cement, 700 kg of sand, and 1050 kg of aggregate. The total volume for these materials should add up to 1 cubic meter when factoring in the mixing process and compaction. Adjustments can be made based on specific project requirements or desired concrete strength.


How much sand and aggregate required 1 cubic meter of M30 grade cement?

Type your answer here... 11.2


Convert 1 cubic meter of aggregate to kg?

The density of aggregate can vary, but on average it is around 1.5 tonnes per cubic meter. Therefore, 1 cubic meter of aggregate would weigh approximately 1500 kg.


How many cube test required for 1 cubic meter concrete?

0.2


How much sand is required for one cubic meter of concrete for slab?

For one cubic meter of concrete used in a slab, approximately 0.3 to 0.5 cubic meters of sand is typically required, depending on the specific mix design. A common concrete mix ratio for slabs is 1:2:4 (cement:sand:aggregate), which translates to about 0.4 cubic meters of sand for each cubic meter of concrete. However, the exact amount may vary based on the desired strength and workability of the concrete.